redzilla
All tools
Power

Generator Sizing

Enter the running load, power factor and motors to start and I compute the generator capacity (kVA) with margin, the starting peak and the altitude/temperature derate.

kW

Total active power in normal operation, excluding the starting transient.

PF

kVA = kW / PF. Mixed loads usually sit around 0.80.9.

Headroom over the running load for future growth. Typical 2030 %.

Motor to start (optional)
kW

The largest motor that starts cold. Leave 0 if there are no large motors.

Starting method

Apparent starting inrush: DOL ~6×, Y-Δ ~3×, soft starter ~2×.

Above 1000 m: −3.5 % per 300 m.

Above 40 °C: −2 % per 5 °C.

Examples
redzilla.cl — genset
 
Nominal generator
after margin and derate
Running kVA
base load
Starting peak
motor transient
Nominal
Running
Peak

Calculation breakdown

ItemValueDetail
How it is computed · running, starting and derate

1. Running load in kVA: kVA_run = kW / PF.

2. Recommended with margin: kVA_rec = kVA_run × (1 + margin).

3. Starting peak of the largest motor: kVA_start = (kW_motor / PF) × factor (DOL 6×, Y-Δ 3×, soft starter 2×). The generator must cover max(kVA_rec, kVA_start).

4. Site derate: altitude above 1000 m −3.5 % / 300 m; temperature above 40 °C −2 % / 5 °C. Combined factor f = (1 − d_alt) × (1 − d_temp).

5. Required nominal: kVA_nominal = kVA_rec / f.

! This is an estimate. The starting peak is transient (seconds) and depends on the load torque; check the manufacturer's voltage-dip curve and the motor type. Validate the real PF and expected growth before you buy.

Runs locally in your browser · no sign-up · nothing leaves your browser

How it works

The calculator sizes a generator set from the running load in kW and the power factor: it converts to apparent power with kVA = kW / PF, adds a configurable reserve margin (typically 20–30 %) and compares that value against the starting peak of the largest motor, computed as (motor kW / PF) × factor depending on the method: direct-on-line DOL ≈ 6×, star-delta ≈ 3× and soft-starter ≈ 2×. The generator must cover the larger of the two.

It then applies the site derate: above 1000 m of altitude it subtracts 3.5 % per 300 m and above 40 °C ambient it subtracts 2 % per 5 °C, combining both factors as f = (1 − d_alt) × (1 − d_temp). The recommended nameplate rating is kVA / f, and the breakdown shows whether the size is driven by the running load or by the starting transient. It is an estimate: the peak lasts seconds and depends on the load torque, so validate against the manufacturer voltage-dip curve.

Example: 40 kW load with a 10 kW motor on direct-on-line start

  1. Running: 40 kW / 0.8 = 50 kVA; with a 25 % margin: 62.5 kVA.
  2. Motor start: 10 / 0.8 = 12.5 kVA × 6 (DOL) = 75 kVA peak.
  3. With no derate (below 1000 m and 40 °C), the rating is max(62.5, 75) = 75 kVA: here the starting peak, not the running load, sets the size.

Frequently asked questions

How many kVA does a generator need for a 100 kW load?
At a power factor of 0.8 the running load is 125 kVA, and with a 25 % margin the recommendation rises to about 156 kVA. If large motors start direct-on-line, the peak may demand a bigger unit: that is why the calculator always compares running-plus-margin against the starting transient.
What happens if I install the generator at altitude or in hot weather?
The combustion engine loses power in the thinner air and the alternator loses capacity with temperature. The rule used is −3.5 % per 300 m above 1000 m and −2 % per 5 °C above 40 °C. At 3000 m, for example, the altitude derate reaches about 23 %, so a 100 kVA unit delivers close to 77 kVA.
What is the difference between direct-on-line, star-delta and soft-starter?
It is the overcurrent the motor demands at start: direct-on-line (DOL) draws about 6 times its running kVA, star-delta about 3 times and a soft-starter about 2 times. Changing the starting method of a large motor can allow a considerably smaller generator, because the starting peak is often what sets the size.
Why are generators rated in kVA and not in kW?
Because the alternator is limited by current (apparent power, kVA), while the useful kW depend on the load power factor: kW = kVA × PF. A 100 kVA generator delivers 80 kW at PF 0.8. That is why the calculator asks for the load kW and the PF separately.
Was this tool useful?
Disclaimer We take great care to keep every tool accurate and review it thoroughly; even so, we can't guarantee it is free of errors or take responsibility for how the results are used. We recommend double-checking anything critical.
Found an error? Let us know →